August 7th Update
This is the first of what we plan to be frequent ongoing updates from our Community. These are meant to be quick explanations of what the community and the board are working on.
This week, we are continuing roof replacement on 5 of our 18 buildings. This should be completed by next week. Gutters were cleaned out yesterday, August 6th, and will be done biannually going forward.
The remainder of roofs are planned to be completed during the Windhover Renovation Project projected to start in 2026. The Association has submitted an application for a $3,500,000 loan. This project will include replacing all remaining roofs, new sheathing, building wrap, Hardie Siding, gutters, downspouts, and paint along with several deck and fence replacements. This project is scheduled to be completed over the course of 1 year, and we will release updated information as we continue to work through this.